DTA-2508 · Doral, FL

Doral Tech Annex

Owner entity
Doral Tech Owner LLC
General contractor
Meridian Builders
Contract value
$41M
Notice to proceed
Apr 8, 2026
Substantial completion
Oct 10, 2027

Subcontracts

SubcontractorTradeContractValueStateFindings
Vista Plumbing Co
Dwayne Eze
Fire ProtectionSC-DTA-2508-038$8,200,000At risk1H
Ironwood Interiors
Nadia Jessup
RoofingSC-DTA-2508-039$5,600,000At risk1H
Quarry Ridge Concrete
Imani Rossi
Structural SteelSC-DTA-2508-035$8,200,000Clear
Coquina Waterproofing
Nadia Lindqvist
Finish CarpentrySC-DTA-2508-036$8,200,000Watch1M
Cordova Glass Systems
Priya Duffy
MechanicalSC-DTA-2508-034$2,400,000Clear
Union Point Electric
Elena Duffy
PlumbingSC-DTA-2508-037$2,400,000Clear

Findings on this project

HighCOI-UMB-LIMIT-LOWVista Plumbing Co

Umbrella limit is $2,500,000 against a required $5,000,000

observed $2,500,000required $5,000,000source coi_umbrella_38_295.pdf p.3
HighCOI-AI-MISSINGIronwood Interiors

Additional insured endorsement is required by the subcontract and is not shown on the certificate

observed not shownrequired requiredsource coi_gl_39_299.pdf p.1
MediumCOI-WOS-MISSINGCoquina Waterproofing

Waiver of subrogation is required by the subcontract and is not shown on the certificate

observed not shownrequired requiredsource coi_gl_36_278.pdf p.2