WYN-2304 · Miami, FL

Wynwood Yards Mixed Use

Owner entity
Wynwood Yards Holdings LP
General contractor
Vantage Construction Group
Contract value
$96M
Notice to proceed
Aug 21, 2025
Substantial completion
Jan 3, 2027

Subcontracts

SubcontractorTradeContractValueStateFindings
Everglade Electric
Renee Fontaine
PlumbingSC-WYN-2304-014$2,400,000Stop work1C 1H
Keel Earthworks
Lorraine Lindqvist
LandscapeSC-WYN-2304-012$8,200,000Stop work1C
Windward Fire Protection
Priya Fontaine
ElevatorsSC-WYN-2304-013$780,000At risk1H
Quarry Ridge Concrete
Imani Rossi
Structural SteelSC-WYN-2304-018$12,500,000Watch1M
Sandpiper Glazing
Dana Boone
MechanicalSC-WYN-2304-015$8,200,000Clear
Anchor Bay Foundations
Yasmin Jessup
LandscapeSC-WYN-2304-017$8,200,000Clear
Flagler Systems Group
Emeka Okonkwo
Structural ConcreteSC-WYN-2304-016$3,900,000Clear
Tradewind Mechanical
Marcus Castellanos
ElectricalSC-WYN-2304-019$420,000Clear

Findings on this project

CriticalCOI-GL-EXPIREDKeel Earthworks

General liability certificate expired 23 days ago

observed 2026-08-14required 2026-09-06source coi_gl_12_92.pdf p.1
CriticalDOC-MISSING-WCEverglade Electric

Workers compensation certificate has never been received for this subcontract

observed not on filerequired required
HighCOI-WC-LIMIT-LOWEverglade Electric

Workers compensation each-accident limit is $0 against a required $1,000,000

observed $0required $1,000,000
HighCOI-AI-MISSINGWindward Fire Protection

Additional insured endorsement is required by the subcontract and is not shown on the certificate

observed not shownrequired requiredsource coi_gl_13_100.pdf p.1
MediumCOI-WOS-MISSINGQuarry Ridge Concrete

Waiver of subrogation is required by the subcontract and is not shown on the certificate

observed not shownrequired requiredsource coi_gl_18_139.pdf p.1